News: Oceania Marine’s North Shipyard working on major upgrades of Damen Sea Axe Shadow Support Yacht UMBRA

August 13, 2014 by black
View large version of image: Oceania Marine's North Shipyard working on major upgrades of Damen Sea Axe Shadow Support Yacht UMBRA

The project is scheduled to be completed within the next three months and includes, a two metre addition to the stern, fitting of helicopter deck and all equipment and infrastructure supporting helicopter operations. At the same time a full exterior repaint in owners colours and vessel survey requirements will be done.

Oceania Marine’s Brent Charlesworth is Project Manager and explains: “We are working to a very tight schedule and have a lot to do within the timeframe. As a consequence we have put together a work team involving our best workers, sub-contractors and suppliers available from within Port Whangarei.”

Luxury yacht support vessel Umbra has been transferred from the hardstand into Refit/Paint Shed C where she will stay for the duration of the project. Crew and owners representatives have made themselves comfortable in the newly upgraded crew amenity and work areas with direct access at deck level.

Add a Related Photo | Add a Related Video 


No Comments - Share Your Thoughts

Leave a comment

You must be logged in to post a comment.

More Oceania Marine's North Shipyard working on major upgrades of Damen Sea Axe Shadow Support Yacht UMBRA Information:

  1. Singapore Yacht Show 2014 to feature superyacht EXUMA for the first time
    black

    News: Singapore Yacht Show 2014 to feature superyacht EXUMA for the first time

    April 1, 2014 by black

    Briand’s extensive experience on the professional racing circuit and designing sailing yachts means he has a particularly heightened awareness of hull structure optimization. This is a quality required of all …


  2. New contract for sale of Darwin Class 86' Yacht signed by CdM
    black

    News: New contract for sale of Darwin Class 86′ Yacht signed by CdM

    March 10, 2014 by black

    The shipyard confirms its remarkable performances, as proved by the outstanding results. Ennio Cecchini, CEO of Cantiere delle Marche, shows some numbers of 2014/15/16, that highlight a +50% of the …


  3. Damen 67m SEA AXE 6711 Fast Yacht Support Vessel undergoes successful sea trials
    lucy

    News: Damen 67m SEA AXE 6711 Fast Yacht Support Vessel undergoes successful sea trials

    January 27, 2014 by lucy

    Due for delivery ahead of schedule in January 2014, 6711 superyacht support vessel has been configured with an extensive dive centre, including its own decompression chamber. Deck space, excluding fully …